OBSC1 Paving Progress Update - 5/22
OBSC1 Members: Please see below for an end of week update on our paving project. We will continue to keep you all updated on project progress.
Paving Schedule
The crew made good progress again on Friday, 5/22. As a reminder, asphalt remains hot long after the crews have completed their work, so please use caution, especially with children and pets. Additionally, with the higher temperatures this weekend, the asphalt can take additional time to 'cure,' so the roads paved yesterday remained closed until this afternoon - they have now been reopened as of 2:30pm. As mentioned, the project is taking longer then originally anticipated. Late on Monday, the crew will shift over to handle milling and paving of one street in Rutherford, with plans to return to OBSC1 on Tuesday. See below for a summary of progress and planned activity by street, schedule subject to change. Hyperlinked road names contain pictures of the roads for anyone interested.
E Shore | completeE Surf | completeE Spray | completeE Channel | completeE Beach | complete, road re-opened at 2:30pm todayE Bay | complete, road re-opened at 2:30pm todayE Barnegat | scheduled for milling and paving on Monday, 5/24 and will be closed to traffic through Tuesday, 5/25 early afternoonOcean Rd | milling complete, scheduled for paving on Monday, 5/24 and will be closed to traffic through Tuesday, 5/25 early afternoonIn order to mitigate traffic on Ocean Road, which is heavily traveled given it's access to all streets on the east side, we have hired security personnel to ensure cars, and most importantly delivery trucks, do not travel on the new road surfaces until they are curedW Shore | milling and paving scheduled to take place between Tuesday, 5/25 and Wednesday, 5/26W Surf | milling and paving scheduled to take place between Tuesday, 5/25 and Wednesday, 5/26W Spray | milling and paving scheduled to take place between Tuesday, 5/25 and Wednesday, 5/26W Channel | milling and paving scheduled to take place between Tuesday, 5/25 and Wednesday, 5/26W Beach | milling and paving scheduled to take place between Tuesday, 5/25 and Wednesday, 5/26W Bay | prep work will begin on Sunday, 5/23 with patching to follow on Monday, 5/24W Barnegat | milling and paving scheduled to take place between Thursday, 5/27 and Friday, 5/28Residents on west side streets that are impacted by road closures are welcome to park in the marina parking area while your particular road is impassable. Please keep a sign with your address/phone number in the window in case we need to get in contact with you during that time.
Trash Collection Update
Contrary to our update on 5/20, TRASH COLLECTION WILL TAKE PLACE ON MONDAY, 5/24 as scheduled. We have arranged for the trucks to pass through our streets prior to 8am to avoid conflicts with paving equipment and driving on newly paved surfaces.